  400.2-610.  Anticipatory repudiation. — When either party repudiates the contract with respect to a performance not yet due the loss of which will substantially impair the value of the contract to the other, the aggrieved party may

  (a)  for a commercially reasonable time await performance by the repudiating party; or

  (b)  resort to any remedy for breach (section 400.2-703 or section 400.2-711), even though he has notified the repudiating party that he would await the latter's performance and has urged retraction; and

  (c)  in either case suspend his own performance or proceed in accordance with the provisions of this article on the seller's right to identify goods to the contract notwithstanding breach or to salvage unfinished goods (section 400.2-704).

­­--------

(L. 1963 p. 503 § 2-610)

(1977) Held, that notice that delivery under contracts to be performed would not be made unless payment for goods already delivered under other contracts with same buyer was made constitutional anticipatory breach by repudiation of the contracts under which delivery had not been made. National Farmers Organization v. Bartlett & Co., Grain (C.A. Mo.), 560 F.2d 1350.


---- end of effective  28 Aug 1963 ----

use this link to bookmark section  400.2-610


Click here for the Reorganization Act of 1974 - or - Concurrent Resolutions Having Force & Effect of Law
In accordance with Section 3.090, the language of statutory sections enacted during a legislative session are updated and available on this website on the effective date of such enacted statutory section. Revisor Home    

Other Information
 Recent Sections Editorials May Be Cited As Tables & Forms Multiple Enact
Repeal & Transfer Definitions End Report

Site changes Pictures Contact

Other Links
Legislative Research Oversight MOLIS
Library MO WebMasters
Senate
Missouri Senate
State of Missouri
MO.gov
House
Missouri House